The
new biomass-fuelled Nova Scotia Power co-generation plant is now humming at
full capacity at the Port Hawkesbury Paper site in Point Tupper.
Mark
Sidebottom, NSP's vice-president of power generation and delivery, said on
Tuesday the commissioning comes after a 120-hour final testing process last
week.The plant has been under construction for two years and the commissioning process has taken the last six months. The $200-million project came in on budget as expected.